  • Our budget request was accepted! Let's work out a timeline
  • Work on RSO - ASO model clauses more – can we get to "beta" quality today?
  • How are invitations to our April 15 meeting going?

Attending: Eve, Andrew, Ann, Adrian, Mark, Kathleen

Budget request accepted

The Kantara board has asked us for a cash flow timeline. Eve's estimate was that we could develop our requirements by early Q3, say no later than July, and identify a contractor by early-mid Q3, and ideally conclude the project by the end of Q3 (Sep). This gives us a forcing function to have a credible set of beta model text to work with by Q2. We seem to be able to accept this, even though there are some question marks.

AI: Eve: Reach out to our community of "legal eagle" participants to wake up active participation once again.

Realistic first beta review timelines

Is it realistic to invite anyone to our Apr 15 call? Are we ready with text? There are two parts to this: Can external parties attend, and do we have enough text/materials?

Adrian proposes that Kathleen is on the critical path here. Kathleen just wants to run a FHIR pilot based on our clauses! And doesn't see Andrew's use case as incompatible. What's most practical? Kathleen suggests that getting to the point of real clauses is really the most practical. The FHIR connectathon is in May. She would like to "XMLize" the clauses for that target. What actual language is being executed here (since XML is just the "punctuation", if you will), if FHIR has a place in the code for a Grantor etc.? It sounds like they are using UMA authorization servers to consume standardized policy expressions in XML (if not necessarily XACML) format, and this would map to the Grantor's wishes for sharing. This could come down to a particular set of trust relationships, and the question of whether it splits into "active" policies vs. things like consent receipts.

Our Grantor - RqP (Grantee?) trust relationship already mentions consent receipts, and we've already discussed how CRs need to be part of a workflow that shows the Grantor what it is they're consenting to (or proactively sharing/delegating or whatever, i.e. setting a policy/sharing preference), so we could already be in the ballpark here. FHIR is using its audit logging framework for this workflow.

Adrian had made a generic "NPE Release of Information Form 1" sample form a few months ago, and Kathleen observes that with a few additions this could be something like what FHIR needs. Adrian is intending this to be used by the RS/RSO for setting up phase 1 (that is perhaps a rathole for our purposes for today's agenda; Eve suggests that Adrian and Kathleen discuss offline as appropriate).

Eve shared a slide deck that runs through various design patterns for splitting the technical resource subject and legal Grantee roles. This deck now has some explanation on the first slide about how the technical UMA flow can stay the same, while the trust relationships and legal/contractual backing might vary significantly.

...