2014 Roadmap Summary Chart
Expand | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||
For Month Cells:
For Activity Column:
|
Activity | Q1 | Q2 | Q3 | Q4 | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
FICAM TFP (Trust Framework Provider) | ||||||||||||
Review of SECs | ||||||||||||
S3A Guide - 3520 | ||||||||||||
Review and rewrite the old profile rules | ||||||||||||
Overhaul IAF document | ||||||||||||
Modular IAF Model Report | ||||||||||||
Resilient Trust Networks Phase 1 | ||||||||||||
Relying Party Guidelines | ||||||||||||
Privacy Assessment Criteria | ||||||||||||
IAF Alignment with ISO 29115 | ||||||||||||
Key Signing Ceremony Analysis | ||||||||||||
IAF SAC Relationship to Safe Harbour Regulations | ||||||||||||
Regular monitoring of ISO29003 drafts |
2014 Roadmap Details
...
Expand | ||
---|---|---|
| ||
Activity:
Activity Type:
Start+End Quarters:
Resources:
Source:
Status:
|
TBD= To be determined |
Activity | Priority (Urgency, Importance H|M|L) | Activity Type | Start+End Quarters | Resources | Source | Status | |||
---|---|---|---|---|---|---|---|---|---|
FICAM TFP | H | recommendation | Q3 | Rich Furr |
| ||||
Review SECs | L | Peter A., Scott Shorter, Rich Furr | |||||||
S3A Guide - 3520 | H | Q3 | Richard Wilshire |
| |||||
Overhaul IAF document | H | Q3 |
| ||||||
Review and rewrite the old profile rules | M | ||||||||
Privacy Assessment Criteria | IAF Updates | Pending | M | Report | TBD | TBD | Carried over from 2013 |
| |
Modular IAF Model Report Identification of Work Edits and Publication (this work must align with the comparability work) | Report | Andrew Hughes ) A paper describing the functional elements of a generalized Assurance Framework, model of interactions and deployment patterns. Intended to inform potential partitioning of SAC by Role. | Report | Q2 | Andrew Hughes (L), Ken Dagg, Scott Shorter, Cathy Tilton, Myisha Frasier-Mcelveen Lack of available time is delaying work on this itemRichard Wilsher | Carried over from 2013 |
| ||
Relying Party Guidelines | Report
| Pending | Recommendation | Q2 | TBD | Carried over from 2013 |
| ||
IAF Alignment with ISO 29115 | Report
| Pending | Recommendation | TBD | TBD | Carried over from 2013 |
| ||
Key Signing Ceremony -Analysis A report on analysis and impact to SAC
| Report | TBD | Lead required Scott Shorter to support | Carried over from 2013 | 2014-03-06: Priority, scope and impact need to be defined. | ||||
Resilient Trust Networks Sub-GroupPhase 1 Delivery of Phase 1 deliveryresults | Report | Q1 | Patricia Hammar (L), Ken Myers IAWG Volunteers TBD | Carried over from 2013 | 2014-03-06: On track for delivery end-Q1 or early-Q2 2014 | ||||
IAF SAC Relationship to Safe Harbour Regulations Produce a Report on how the IAF SAC might or might not cover requirements of Safe Harbour (for Kantara consumption) | Report | TBD | TBD | IAWG Meeting Minutes 2014-01-09 |
|