2013 Roadmap & Deliverables

Qtr

Deliverable

Resources

Status

Q1

Privacy Assessment Criteria

Pending

Awaiting handover from P3. IAWG will review this work from an identity perspective.

Chair to confirm handover interface and timing.

 

Q2

Q3

Decoupled Binding -

Identification of Work

Edits and Publication (this work must align with the comparability work)

Andrew Hughes, Ken Dagg, Scott Shorter, Cathy Tilton, Myisha Frasier-Mcelveen

 

Lack of available time is delaying work on this item

 

Q2

Q2

IAF Alignment with 800-63-2

Analysis

Completion (revised SAC)

Richard Wilsher

In Progress

Completion includes review, feedback, remediation. Feedback cycle may be of variable length.

Will also result in recommendation to NIST for future revision of 800-63-2.

Q2

Relying Party Guidelines

Pending

Not launched; needs renewal of discussion; Chair to solicit IAWG for input into scope

Q2

IAF Alignment with ISO 29115

Pending

ISO29115 is a basis document for ISO29003

Q3

IAWG Review and Contribution to Draft ISO29003

Pending

When ISO29003 draft is published next in April 2013, decision required for next steps and approach to discuss provide comment.

Q3Key Signing Ceremony - analysis and impact to SAC

Lead required

Scott Shorter to support

 
Q4Resilient Trust Networks Sub-Group Phase 1 delivery

Patricia Hammar, Ken Myers

IAWG Volunteers TBD

 

2012 Roadmap & Deliverables

Qtr

Deliverable

Resources

Status

Q1 - Q2

Document set maintenance 

  • Phase 1
     
    • Merge FICAM-approved v0.9 with IAWG-approved v2.0
    • Restructure the SAC to allow a component-based approach by auditing entities.
    • Amalgamate and depose pilot feedback. Incorporate ARB due diligence reports and implement edits where applicable in the AQR and AAS.
  • Phase 2
    • Discuss the concept of separating identity from a credential and how this would affect the IAF or could be incorporated.
    • Present the updated IAF document set to FICAM for acceptance (if applicable). 

Editor: RGW

  • SAC restructured Review in progress.
  • Edits from pilot feedback and ARB due diligence report in progress.
  • FICAM has been made aware of IAWG intentions and progress.

Q2

Kantara Assessment Review  (KAR)

  

Q3-Q4

Privacy Assessment Criteria

Pending

Awaiting handover from P3. IAWG will review this work from an identity perspective.

???

Relying Party Guidelines

Pending

Not launched.

???

Alignment with 800-63

Pending

Not launched.

2011 Roadmap & Deliverables

Qtr

Deliverable

Resources

Status

Q1

Finalize v1.0 Federation Operator Guidelines [FOG]

David Wasley

Doc Approved by All-Member Ballot on 30 Jan 2011

Q1

SAC Profiling Guidelines v1.0 [SAC]

Myisha Frazier McElveen, Ben Wilson, Rich Furr

Complete

Q2

Form Attribute Assurance Charter + WG

John Bradley

AMDG created September 2011.Complete.

Q2

Form SAC Profile Development WG

Dazza Greenwood

Not Progressed

Q2 - Q3

Define Trust Framework Architecture

Rainer Hoerbe, Patrick Curry, Ken Dagg

Effort removed from IAWG. TFW MM WG created 30 March 2011 on approval by the LC

 

 

 

 