Subgroup Work Plan and timelines
Work plan
- Step one: identification: Analyze the source texts with the rules above to create a list of the requirements and recommendations.
- Step two: tagging. Tag the requirements to identify which ones belong to which AL, as well as which entities the requirement applies to, and any conditionality in the requirements. (WHAT, WHO, WHEN)
- Step three: express assessment methods. Could include a list of standard evidence, common assessor and assessee activities, reporting templates…?
Timelines
Schedule: 11 meetings, 10 weeks
Step zero: find any pre existing work products to include in the mix
Step one: identification 8/10-8/31
Step two: tagging 8/31-9/14
Step three: assessment methods 9/14-10/19