2025-03-27 IAWG Meeting Notes

2025-03-27 IAWG Meeting Notes

Meeting Status Metadata

Quorum

quorate

Notes-Status

approved

Approved-Link

2025-04-10 IAWG Meeting Notes

The meeting status metadata table is used for summary reports - copy the status macros from the table in these instructions:

Quorum: quorate not quorate

Notes-Status: drafting Ready for review approved

Approved-Link: Insert a link to the Meeting Notes page holding the approval decision for this notes page

Agenda

DRAFT 01.23.2025 

  1. Administration:

  • Roll call, determination of quorum. 

  • Minutes approval 

    • Deferred

  • Kantara Updates

    •  

  • Assurance Updates

  1. IAWG Actions/Reminders/Updates:

    •  

  2. Group Discussion:  

 

 Attendees

Voting Participants 

Donald, India

GSA

 

Hughes, Andrew

FaceTec

Present

Jung, Jimmy

Slandala 

Present

Magrath, Michael

Easy Dynamics

Present

Silberstein, Yehoshua

Notarize

Present

Stojkovski, Vladimir

CLEAR

 

Wilsher, Richard

Zygma Inc. 

Present

 

Nonvoting:

Brown, Wendy

FPKI

Present

Bachenheimer, Dan

Accenture

Present

Brown, Cynetheia

FPKI

Present

Anderson, Tim

ID. me

Present

Aronson, Marc

 

Present

King, Mark

 

Present

 

Staff:

Buttle, Carol

Kantara

Present

Chopard, Kay

Kantara

Present

 

Guests:

 

 

 

Quorum determination

Meeting is quorate when 50% + 1 of voting participants attend

There are 7 voters as of 2025-03-27

 

Approval of Prior Minutes

Motion to approve meeting minutes listed below:

Moved by:

Seconded by:

<< Defer to next meeting>>

 

 

 Discussion topics

LINKS TO THE ISSUES TRACKER DATABASE ADDED 2025-07-17 BY A. HUGHES

Time

Item

Presenter

Notes

Time

Item

Presenter

Notes

 

US Assurance Program updates

Kay/Carol

  • Applications are spinning up after a slow start to the year, including non-US companies wanting to do US business

 

General issues

All

  • YS: Some CSPs consider that the NIST 800-63 requirements are not really structurally built to meet the needs of “current” service provider implementations. Today, CSPs sub-contract many functions - and this is hard to capture and ends up in increased complexity.

  • Industry input would be useful - to see if there’s an improvement to be had to better align to actual implementations?

  • An example: GSA has internal forms to determine which services are offered by which applicants to the GSA SIN

  • IAWG must be clear about approach and scope - is it time to break away from strict 800-63 organization? or is it time to do a more broadly applicable set of requirements?

  • This could be an opportunity to engage a broader range of stakeholders - this could be a significant shift so we want to be sure that we are making sound decisions.

  • To be continued…

 

 

 

Kantara staff to update 63A#0680 to "Withdrawn - this referenced biometrics used as an authentication factor, not in the identity proofing process"

 

Kantara staff to update the label OPB#0490 in the OP_SAC which is repeated 4 times, to OPB#0490 and OPB#0500 as indicated in the attached PDF.

 

Kantara staff to change 63A-T5-3#strg FROM:
"biometric comparison of the applicant to the identity evidence. Biometric comparison performed remotely SHALL adhere to all criteria 63A#0620 to 63A#0680 inclusive."
TO:
"biometric comparison of the applicant to the strongest piece of identity evidence provided to support the claimed identity. Biometric comparison performed remotely SHALL adhere to all criteria 63A#0620 to 63A#0680 inclusive."

 

Tim Anderson to gather proposals for discussion in a future meeting

 

 

 

 Open Action items

Action items may be created inline on any page. This block shows all open action items from all meeting notes.

 Decisions